in Rietberg
Mershbrock-Wiese Production hall

Rietberg

11,200 sqm

79 / 66 / 12.00 m

Production facilities

precast reinforced concrete elements and structural analysis

Oct. 2009 – Dec. 2009

Description of the facility
With this newbuild project, Merschbrock-Wiese Gewürzhandel GmbH extended its production and storage capacities as well as its office premises. The two-storey production and storage area features a 16.5 m span BREMER floor with a live load of 20 KN/qm. The three-storey office is accessed via a bridge and is visually emphasized and distinguished from the production facility by a projecting surround finished in company red.
Special features
This project for BREMER comes directly from the client, awarded because of the economical use of the BREMER floor solution.